TABLE 15
ROAD CONSTRUCTION PROJECTS
1 of 2
        FISCAL YEAR (FY)    
ROAD CONSTRUCTION PROJECTS COSTS ($000) /  PROJECT PHASE (SEE TABLE 4) FUND  
PROJECT DESCRIPTION MAP   TYPE FY FY FY FY FY CODE FED
(FINANCE NUMBER) # MILE WORK 01-02 02-03 03-04 04-05 05-06 Table 3 FUNDS
Alachua County- Roadways - - Inspection of miscellaneous 300 CST     700 CST 700 CST     DDR NO
AT: Countywide     road construction projects                     DS  
(2077601)                              
                               
Alachua County- Bridges - - Inspection of miscellaneous     500 CST 500 CST 500 CST 500 CST BRRP NO
AT: Countywide     bridge projects                        
(2077602)                              
                               
Alachua County - - Transportation system 100 CST 100 CST 100 CST 100 CST 100 CST LF NO
AT: Countywide     management (TSM)              
                     
                               
SW 5th Avenue 1 0.1 Streetscaping with bicycle and 150 CST         LF NO
FM: SW 13th Street     pedestrian modifications              
TO: SW 12th Street                    
                               
NW 17th Street 2 0.2 Reconstruction; 400 CST         LF NO
FM: W University Avenue     Streetscaping with sidewalks &              
TO: NW 3rd Avenue     bikelanes to NW 5th Avenue              
                               
SW 24th Avenue 3 3.0       LF NO
FM: SW 62nd Boulevard     Right-of-way acquisition       (These funds may be included in the FDOT project # 2113652)    
TO: SW 34th Street     (funded FY 00-01)          
                 
FM: SW 43rd Street     Construct new 2-lane road 3,250 CST      
TO: SW 34th Street     including bikelanes and        
      sidewalks                        
Main Street 4 1.0 2-lane reconstruction 100 RRU 5,264 CST     300 INC     DDR NO
FM: Depot Avenue     including parallel parking,     38 CST             DIH  
TO: NW 8th Avenue     bus bays & instreet bike lanes                        
(2077851)                              
NW 45th Avenue 5 0.7 Road reconstruction, 2,000 CST         LF NO
FM: NW 24th Boulevard     adding bike lanes              
TO: NW 13th Street     and sidewalks              
                     
NW 19th Street   0.5 Road reconstruction, includes              
FM: NW 39th Avenue     sidewalks on both sides              
TO: NW 45th Avenue     [pending ROW acquisition]              
                               
NW 29th Road 6 0.6 Road reconstruction, includes           LF NO
FM: NW 19th Street     sidewalk on south side              
TO: NW 13th Street     [on hold]              
                     
NW 19th Street   0.5 Road reconstruction, includes              
FM: NW 29th Road     sidewalks on both sides              
TO: NW 39th Avenue     [no bicycle facilites]              
      [pending ROW acquisition]                        
SR 26A / SW 2nd Avenue 7 1.8     1,744 ROW           LF NO
FM: W 38th Street     construct a two-lane divided         529 CST     DIH  
TO: W 34th Street     facility with bikelanes,         3,309 CST     DS  
      sidewalks and raised                  
      landscaped medians                  
                         
FM: W 34th Street     Resurface existing two-lane                  
TO: North/South Drive     facility with sidewalks on the                  
(2077901)     northside and a multi-use                  
      facility on the southside and                  
      add bikelanes on both sides                  
      from W 34 Street to Golfview                        
me\p\tip\tip0106\tblcnstr.wk4
55  
TABLE 15 (Continued)
ROAD CONSTRUCTION PROJECTS
2 of 2
        FISCAL YEAR (FY)    
ROAD CONSTRUCTION PROJECTS COSTS ($000) /  PROJECT PHASE (SEE TABLE 4) FUND  
PROJECT DESCRIPTION MAP   TYPE FY FY FY FY FY CODE FED
(FINANCE NUMBER) # MILE WORK 01-02 02-03 03-04 04-05 05-06 Table 3 FUNDS
North-South Drive Extension 8 0.2 Extend 4-lane facility   650 CST       PECO NO
FM: SW 16th Avenue                    
TO: Archer Road                    
                               
Archer Road Reconfiguration 9 0.3 Reconfigure Archer Road/SW   540 CST       PECO NO
Phase 1     16th Avenue intersection and              
FM: SW 16th Avenue     rebuild road to primarily serve              
TO: North-South Drive     buses, bikes and pedestrians                        
Archer Road Reconfiguration 10 0.8 Change roadway profile through   560 CST       PECO NO
Phase 2     the Health Center Complex              
FM: North-South Drive                    
TO: SW 13th Street                              
North-South Drive 11 - Construct a consolidated facility     490 CST     PECO NO
Multimodal     to accommodate buses, bicycles              
Transportation Center     and automobile passenger              
AT: Stadium Road     dropoffs                        
State Roads 26/26A 7,12 1.9 Streetscape project       1200 CST   LF YES
Enhancement     [coincides with SR 26       1230 CST   SE  
FM: W 38th Street     resurfacing- FMN 2078171              
TO: North/South Drive     and SR 26A reconstruction-              
(FMN to be assigned)     FMN 2077901]                        
me\p\tip\tip0106\tblcnstr.wk4
56